Table of Contents
Brief Explanation
BC Strategies in Five Points
From BIA to Strategy
What a Strategy Must Address
Gap Analysis
Check & Secure
Four Approaches
Prevent, Shorten, Limit, Bridge
Options per Resource
Personnel, Locations, IT, Suppliers and More
Basic Patterns
Redundancy, Diversion, Alternative Procedures, Buffer, Acceptance
Selection
Effectiveness, Risk and Cost
Decision
Present Options, Do Not Pre-empt
Implementation
From Strategy to Plan
Key Figures
Measure Effectiveness
Conclusion
Solutions for Specific Gaps
Frequently Asked Questions
Insurance, Gaps and Review
Sources
Standards and Guidelines
Brief Explanation
BC Strategies in Five Points
- A Business Continuity Strategy outlines how time-critical activities will be continued or restored in a timely manner when personnel, locations, IT, information, or suppliers fail.
- The starting point is the results of the Business Impact Analysis: target times (RTO, RPO, MTPD), minimum capacities, and the required resources. The gap analysis following the Check & Secure principle shows where the achievable recovery time or data status falls short of the requirements – action is needed there.
- Strategies focus on four areas: preventing failures, shortening their duration, limiting their impact, and bridging the time until recovery.
- Selection is based on three criteria: Does the solution meet the time and capacity requirements, does it align with the accepted risk, and is its benefit in a reasonable proportion to the costs?
- BCM prepares the options as a decision template; the management decides – including which gaps are consciously accepted.
From BIA to Strategy
What a Strategy Must Address
A business continuity strategy (BC strategy) translates the results of the analysis into precautions. The Business Impact Analysis provides three things: which activities are prioritised, by when they must be operational again with what minimum capacity, and what resources they require. The strategy determines how these requirements will be met.[1]
Before solutions are sought, the target picture is established:
- Prioritisation: Which products, services, and processes are critical, and in what order must they be operational again?
- Time and data specifications: Target time for recovery (RTO), maximum allowable data loss (RPO), Maximum Tolerable Period of Disruption (MTPD), and the required minimum performance level in emergency operation.
- Performance requirements: Agreed service levels (SLA) as well as requirements for quality, data, and resources.
- Capacities: how much personnel, IT, operational technology (OT), building space, and service provider performance is minimally necessary.
The core is the comparison between target and actual. The target time for recovery (RTO) is the specification; the actually achievable recovery time (RTA) shows what the existing precautions can achieve. If the RTA exceeds the RTO, a gap arises that a strategy must close or the management must consciously accept. How this comparison proceeds is described in the next section; the basic rule RTA ≤ RTO is explained in the article on RTO, RPO, RTA and SLA.
A BC strategy is therefore not a general commitment to resilience but a collection of specific solutions, each assigned to a resource and a time requirement. A strategy can consist of several solutions, and a solution can secure multiple processes simultaneously – for example, an alternative location where several areas can operate.[1]
Target-Actual Comparison Check & Secure
Check target values, secure gaps
Whether the existing precautions are sufficient is shown by a systematic target-actual comparison. The principle behind this is called Check & Secure: first check what is actually achieved, then secure what is missing.
Check Compare actual state against target values

- Time: compare the target time (RTO) with the actual recovery time (RTA).
- Data: compare the RPO with the actually achievable data status or actual data loss.
- Resources: compare required and actually available resources.
- Evidence: verify SLA fulfilment, data availability, and recoverability through tests and evidence – not assumptions.
- Dependencies: assess bottlenecks and single points of failure, i.e., resources whose failure without alternatives stops one or more time-critical activities.
Secure Secure identified gaps

- Close gaps through organisational, technical, or contractual measures; the following sections show what options are available.
- Address risks from the risk assessment: avoid, reduce, transfer, or consciously accept.
- Document residual risks, responsibilities, and necessary escalations.
The alignment is not a one-time step: results from exercises, tests, and incidents provide new actual values, which are then re-evaluated against the target values.
Four Approaches
Prevent, shorten, limit, bridge
ISO 22301 requires considering multiple directions when searching for strategies and solutions: protecting prioritised activities, reducing the likelihood of disruption, shortening its duration, limiting its impact on products and services, and ensuring the availability of necessary resources.[1] From this, four practical approaches can be derived:
| Approach | Question | Examples |
|---|---|---|
| Prevent | How can the failure of a resource be made less likely? | Redundant power supply, fire protection, maintenance contracts, second network connection |
| Shorten | How can the resource be made available again more quickly? | Agreed recovery times, spare parts inventory, rehearsed restart procedures |
| Limit | How can the damage during the outage be reduced? | Prioritisation of customers and orders, emergency operation with reduced capacity |
| Bridge | How does the activity continue without the resource? | Alternative site, manual substitute procedure, stock inventory, second supplier |
The BSI Standard 200-4 similarly distinguishes between three types of prepared measures: preventive measures reduce the likelihood of a resource failure; business continuity solutions enable continuation in an emergency; emergency measures are prepared but only executed during an event. A typical example of a BC solution is an alternative site, which is prepared in advance and only occupied after a building failure.[2]
For Business Continuity Management, the focus is on the last two approaches. Prevention is usually the task of risk management, information security, or facility management; BCM checks whether the measures in place are sufficient to meet time requirements and supplements what is missing.
Strategy Options per Resource
Personnel, locations, IT, suppliers and more
ISO 22301 specifies the resources for which requirements for the chosen solutions must be determined: personnel, information and data, buildings and work environment including supply, equipment and consumables, information and communication technology, transport and logistics, finances, as well as partners and suppliers.[1] For each of these resources, there are typical options:
| Resource | Typical Options | Considerations |
|---|---|---|
| Personnel | Deputies, cross-training, knowledge documentation, task relocation, use of external personnel | Key knowledge held by only one person; simultaneous failure of many (e.g., pandemic) |
| Information and Data | Data backup at a separate location, replication, paper or offline version of critical documents | Data loss up to the last backup point (RPO); readability without the failed system |
| Buildings and Work Environment | Alternative site (immediately usable, prepared, or just space), mobile working, relocation to other own sites | Readiness level and lead time; dependency on the same power grid or region |
| Equipment and Materials | Spare devices, spare parts inventory, framework agreements for rental or replacement devices | Delivery times for special parts; storability |
| ICT Systems | Redundant systems, alternative data centre, recovery procedures, manual substitute procedures | Whether recovery can be achieved within the target time in practice; dependencies between systems |
| Transport and Logistics | Alternative transport routes and service providers, decentralised warehouses | Bottlenecks when many companies switch simultaneously |
| Finances | Liquidity reserve, credit lines, emergency budget with approval rules | Ability to pay during emergency operations |
| Partners and Suppliers | Second supplier, safety stock, reserved capacity, contractual continuity commitments, in-house production | Whether the alternative is qualified, permissible, and deliverable on time |
For suppliers, a nominally available alternative is only effective if it can actually deliver in an emergency. How this can be tested and when buffering is a better choice than bridging is described in the article Supply Chain Resilience. The same applies to outsourced IT services and providers: The agreed recovery time (SLA) must match the target time of the dependent process.
Basic Patterns of Solutions
Redundancy, Diversion, Alternative Procedures, Buffering, Acceptance
Across all resources, a few basic patterns recur. They help to consider options fully before choosing a solution:
- Redundancy and Distribution: A resource is available multiple times or distributed across several locations, systems, or suppliers. Effective, but often expensive – and only if the redundancy does not rely on the same dependency.
- Diversion and Relocation: The activity moves to another location or team. Preparation and lead time are crucial.
- Alternative Procedures: The activity continues with different means, for example manually instead of system-supported, with reduced scope or for selected customers. This is the classic emergency operation.
- Buffering: Stocks, reserves, and liquidity provide time until the resource is back or an alternative is in place.
- Accelerating Recovery: Contracts, spare parts, and practiced procedures shorten the time to normal operations.
- Justified Acceptance: The gap is not closed because the effort is disproportionate to the risk. This is a permissible strategy if the management consciously decides and documents it.
Insurance is not a continuity solution in the strict sense: It replaces part of the financial damage but does not keep an activity running. Nevertheless, it should be considered in the overall assessment because it can cushion the financial consequences of a consciously accepted gap.
Selection and Evaluation
Effectiveness, Risk, and Cost
ISO 22301 specifies three criteria for selection: The solution must meet the requirements to continue or restore prioritised activities within the specified time and with the agreed capacity. It must match the type and extent of the risk the organisation is willing to bear. And its costs must be weighed against its benefits.[1] Guidelines for strategic decisions are additionally provided by ISO/TS 22331.[3]
In practice, a uniform evaluation of each option with the same questions proves effective:
| Criterion | Evaluation Question |
|---|---|
| Effectiveness | Does the achievable recovery time (RTA) with this solution fall within the target time (RTO), and is the minimum capacity reached? |
| Scope | How many time-critical activities does the solution cover – one or many? |
| Own Dependencies | Does the solution rely on the same resources as what it is meant to secure, such as the same network, service provider, or personnel? |
| Feasibility | How long does implementation take, and who needs to be involved? |
| Cost | What are the one-time and ongoing costs? |
| Benefit | What damage is avoided in the event of a failure – measured by the financial impact over time? |
For the benefit, the financial impact from the BIA is the reference point: How it grows with the duration of the outage and when it exceeds the risk-bearing capacity is described in the article Financial Impact in the BIA. How the effect of a measure on the overall risk can be demonstrated is described in the article Risk Aggregation.
Management Decision
Present options, don’t pre-empt them
BC strategies allocate budget, space and personnel, and determine which gaps an organisation is willing to accept. Therefore, the management makes the decision. BCM prepares the decision, together with the departments and those responsible for the resources.
A robust decision template includes for each gap:
- the affected products, processes and resources with target time and achievable time,
- the financial and qualitative impact if the gap remains,
- two or three options with impact, costs and implementation duration – including the option to accept the gap,
- a justified recommendation.
Accepted gaps are recorded with justification, responsible person and date of the next review. This ensures it is traceable that a risk was not overlooked but consciously borne. How these decisions are anchored in the BCM system is shown in the article Building a BCM System.
From Strategy to Plan
Provide, describe, verify
A decided strategy only takes effect when it is implemented. ISO 22301 requires the chosen solutions to be introduced and their resources provided.[1] This results in three steps:
- Provide: Conclude contracts, set up alternative sites, establish redundancies, data backup and recovery procedures, prepare emergency operations and communication channels, create inventories, appoint and train deputies.
- Describe: Record in the Business Continuity Plans who activates the solution when and how emergency operations and recovery proceed. What belongs in a plan is shown in the article Business Continuity Plan and Disaster Recovery Plan.
- Verify: Demonstrate in exercises and tests that the solution actually meets the target time. How this is done is described in the article Exercises and Tests in BCM.
To keep implementation manageable, each measure is assigned a responsible person, a deadline, a priority, and evidence by which its effectiveness is recognisable. Whether the strategy is effective is shown by tests, exercises, monitoring and regular re-evaluation.
Strategies become outdated when processes, locations, systems or suppliers change. They are therefore reviewed at planned intervals and upon significant changes. In the integrated data model, the target-actual comparison can be continuously tracked, making new gaps visible as they arise.
Measuring Effectiveness
Metrics for the BC Strategy
A Business Continuity Strategy is effective if the actual recovery capability demonstrably meets the defined time, data, quality and resource requirements. Whether this is the case is shown by a few metrics:
| Metric | What it shows |
|---|---|
| RTO Fulfilment Rate | Proportion of recoveries within the RTO |
| RPO Fulfilment Rate | Proportion of recoveries within the permissible data loss |
| SLA Fulfilment | Achieved availability and performance quality |
| Recovery Success Rate | Proportion of successfully tested recoveries |
| Resource Coverage | Available versus required resources |
| Measure Progress | Measures implemented on time in percentage |
| Risk Reduction | Change in risk before and after the measure |
| Evidence Coverage | Proportion of fully documented and verified safeguards |
There are no universally applicable target values for these metrics; each organisation sets them as its own control values. Such a value might be: „At least 80% of prioritised adjustments implemented by the specified deadline.“
The fulfilment and success rates come from exercises and tests; how these are planned and evaluated is described in the article Exercises and Tests in BCM. How the risk reduction of a measure can be reflected in the overall risk is described in the article on Risk Aggregation.
Conclusion
Solutions for Specific Gaps
A good BC strategy is specific: It assigns a solution to each time-critical resource that demonstrably works within the target time, or records why a gap is consciously accepted. Those who evaluate options based on the same criteria, present them to management as genuine choices, and verify implementation in plans and exercises, turn analysis into reliable preparedness.
Frequently Asked Questions
Insurance, Gaps and Verification
Is insurance a BC strategy?
Only as a supplement. Business interruption insurance replaces part of the financial loss but does not keep any activity running. It can mitigate the consequences of a consciously accepted gap but does not replace a continuity solution.
Must every gap between RTA and RTO be closed?
No. Management can consciously accept a gap if the effort is disproportionate to the risk. The decision is justified, documented, and regularly reviewed.
Who develops the strategies?
The BCM facilitates and prepares, while the departments and those responsible for resources such as IT, buildings, personnel, and procurement contribute their knowledge of feasible solutions. The decision is made by management.
How often are strategies reviewed?
At planned intervals, usually during the annual review of BIA and plans, and additionally in the event of significant changes to processes, locations, systems, or suppliers, as well as after exercises and incidents.
Sources
Standards and Guidelines
The information in this article is based on the following sources. No verbatim quotations are taken from paid standards; their contents are summarised.
- DIN EN ISO 22301:2020-06 – Sicherheit und Resilienz – Business Continuity Management System – Anforderungen (ISO 22301:2019). German version EN ISO 22301:2019, Section 8.3. Publisher: DIN Deutsches Institut für Normung e. V., Berlin. Available for purchase through standards trade. ↑
- Bundesamt für Sicherheit in der Informationstechnik: BSI-Standard 200-4 – Business Continuity Management. Version 1.0, 2023; Terms of prepared measures according to Section 2.3. Freely available from BSI. ↑
- ISO/TS 22331:2018 – Security and resilience – Business continuity management systems – Guidelines for business continuity strategy. International Organization for Standardization, Geneva. Available for purchase through standards trade. ↑
Expert in Business Continuity Management (BCM), risk management, and organisational resilience, particularly in the context of critical infrastructures. His focus is on Business Impact Analyses (BIA), risk analyses, and the development and enhancement of BCM and crisis management structures. Within the NOVELEDGE network, he supports organisations in the practical implementation of resilient structures, considering international standards such as ISO 22301, ISO 27001, and ISO 31000, as well as applicable regulations.




